So much work happened in the house this past week. The floor install is all finished except the staircase, the trim and door install went wonderfully and is finished, and the countertops in the bathrooms and kitchen were installed.
Tag: Dome
First Finishes: Tile Stacked, Bricked, and Herringboned
Now that we have had our first year anniversary on official site work (the well was dug a year ago, though site work didn’t start for a bit yet), my husband and I are feeling the push to get the house done and move in.
The drywall has been completed, and finally the finish work can begin
Walls Around My Heart: Plywood and Sheetrock
For a long while now we have been walking through a house of framed 2×4 and 2×6 walls. All of a sudden it seems, there are true walls and the rooms begin to take shape. The change is dramatic. While there is still a day or so of drywall hanging work to do, most of the house’s walls have been placed.
Getting Warmer: Insulation
Spring is finally peeking out from under the heavy blanket of cold and things are starting to thaw. The creek that runs through our property is starting to move. Last year we had a dramatic rise of water, but this year it is behaving itself and staying more or less within its banks.
Rough Approved: Little Stickers of Happiness
Finally! The rough inspections for everything have been completed. The engineering fixes were installed and the large amount of rough electrical work got finished. What a relief. We now have a bit of an over-engineered beam in the basement but compared with what was in place, I’ll take a living room that I can park…
Beams, Brackets and Hurdles: Send in the Engineers
Some very large and stressful issues came up in regards to the supporting structure of our house. While we know that our house is proving to be a challenge for our builder and the subcontractors, the most recent issues had nothing really to do with the fact that our house is shaped differently. We caught…
Wonky Weather: A Merry December
After the big relief of having the roof completed, we had a few weeks of rest on site as some background things were happening. My husband got started on the electrical in his spare time but other than that little happened of note. The weather in November was blistering cold all month. When December started…
Let It Snow?: A roof over our heads
All signs have been pointing to the first snow coming tomorrow. Yesterday as the temperature began its plummet to wintry climes, the first half of the house was completed! It is an enclosed space and protected from the weather. Siding and brick are still to come, but at long last we can take comfort in…
As the Leaves Turn Golden: The road to enclosing
It has been a little while since my last post. My husband and I, as well as our builder, carpenter, and now the roofer, have been scurrying around solving problems. When everything holds its place in sequence, any delay in a decision or solution can be very hard to swallow. So far, at this point, the issues have been solved. Until we find the next of course.
Hurdles we have leapt in the last few weeks have included: Resolving a couple of wrong window sizes that were placed in the print, moving window framing down to meet egress, sorting out how to meet egress on windows we couldn’t move down, replacing some missing custom flashing for the triangular windows, and a few more on the fly design decisions and hurried trips to the hardware/lumber store for last minute vents and such that had to go through the roof.
As it stands, we are so very close to having her (the house) protected against the every hastening winter weather…
Upon this Rock: The foundation
(Retro Post) The foundation and basement of the house took a couple of months. We were nervous, as it was critical that the basement measure exactly to the print in order for the house to fit. unlike a traditional house, the kit measurements were non-negotiable and there was little margin for error. Enter in Superior…